Printing P6 activities -level by separate pages

Alaa Al hajMember for 18 years 11 months
Created
5
2
0

Hi,

could someone tell me how to print the activities but each level in seperate page

i was  aple to do it in P3 but in P6 not succed yet

regards,

5 replies

Oldest first
  1. 0
    Kumar S ·

    Dear, if you are reffering to

    Dear,

    if you are reffering to the WBS Level then you can get like this

    go to grp and sort _ select wbs _untick the indent option

    then go to print preview _page set up _ options _click page break every grp.

    then you will get in seperate pages...

    hope this helps .

     

  2. 0
    Neeraj Agarkar ·

    kumar, this doesnt work for

    kumar,

    this doesnt work for me as it does not allow you to selectively break pages for certian WBS. For example, if I want only a page break for level 3, this method breaks at level 4 also.

  3. 0
    Neeraj Agarkar ·

    kumar, this doesnt work for

    kumar,

    this doesnt work for me as it does not allow you to selectively break pages for certian WBS. For example, if I want only a page break for level 3, this method breaks at level 4 also.

  4. 0
    Kumar S ·

    Dear Neeraj, ok then there is

    Dear Neeraj,

    ok then there is other way around

    create a user defined feild text type (page break)

    then select this in the columns of the actvities table.

    then put the values in the coulmn

    like if you want the 1st WBS in the first page then say it as 1 then fill down all the activities which are to be in this group

    then for the second WBS type 2 and then fill down

    repeat the same for all the WBS  like 3,4,5,

    then after that go to group and sort select this user defined field (page break) in the top before the WBS .

    then go to the font and color make the font size small and color as WHITE by this way you will not see this in the layout.

    THEN PRINT set up options----page break settings -----click it

    you will get the result...

     

     

     

     

     

  5. 0
    Scott Allerdice ·

    are these some kinsa tools or

    are these some kinsa tools or software to use for printing or just name of some useful machines to go for printing stuff? hubshout

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?