Updating Activities in P6
In the Open Standard
Gokulakrishnan GanesanMember for 16 years 4 months
- Created
- 6
- 1
0
Dear Planners,
In P3, if i want to copy the actual dates from an updated programme to a newly copied baseline programme of same project is by simply copy all the activiites from the updated programme and paste in a baseline programme and choose update activities with matching Id's.Then all the actual dates will be assigned automatically in the copied Baseline programme. I want to know is it possible to do like this in P6 or is there any new way to bring the actual dates from an updated programme to baseline programme for same project.
6 replies