How to create a 2wk look ahead schedule in P6

L P6Member for 15 years 8 months
Created
11
4
0

Hi all,

I am still finding my way around P6 and would like to know if anyone can giuve me a step by step outline of how to create a a 2wk look ahead filter. I am familair with creating filters but have never done one for a look ahead.My two main questions are:

  1. Do I use the "Earliest start date"  and "Latest finish dates" instead of "Start" and "Fininsh"?
  2. I aslo want to include all work that is still in progress during the lookahead period regardless of when it starts or will finsh. Is this good practice to include this criteria as part of a look ahead schedule and if yes, how would I do that in combination with the dates filter in question 1 above?

Thanking ou in advance,

LP6

11 replies

Oldest first
  1. 0
    Irfan Khan ·

    Hi, In Primavera P6 ver. 7

    Hi,

     

    In Primavera P6 ver. 7 have built in filter of Two Week Look Ached Schedule.

    If you want to make in manually so here is the procedure of Two Week Look Ahead Sche.

    Go to in Filter > Click New > Give a title of your filer > than chek the perameters like this < Where = Start > in within range of > Value = DD > High Value = DD+2W.

     

    Hope this ill help u.

     

    regards

  2. 0
    L P6 ·

    Irfan,  Thanks for

    Irfan,

     Thanks for commenting. Yes, your suggestion is certainly helpful especially using the "is within range" term.

     

    I aslo wanted to know if it was necessary to aslo incluse a similar "where" clasue for the Finish date and for activities "in progress". I read on another forum that a look ahead schedule should show:

    • all things starting within the look ahead period
    • and finishing within the look ahead period,
    • as well as all things that are in progress withign the look ahead period.

    Do others agree with the above? If  meeting all three criteria is the correct protocool would the following filter be suitable?

     

    Display all rows Parameter Is Value High Value
      Where Start is within range of DD DD+2W
      Or Finish is within range of DD DD+2W
      Or Activity Status equals In Progress   

    Thanks all,

    Regards,

    LP6

  3. 0
    Mohamed Ezat ·

    hiiii  all   concerning

    hiiii  all 

      concerning  schedule  update   i'm   facing  problem  at   cost  loaded  

    after  entering  the  actual  percentges  for   activities   i  found   the  cash flow  values  for  baseline   changed  and  i'm  sure  that  i  didn't  change  the  dates  for  baseline  

    i  appeared  the baseline   separated  and  checked   the  values  of  cash flow   i noted  that it  became  true    but  after  assigning  the baseline   to  my  updated schedule   the   cash flow values   are  changing 

     

     

    plz if  help  if  you  can  and  tell  me  what is the reason 

    thanks

  4. 0
    Mohamed Abdelhady ·

    Hi all , I need to ask how to

    Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?

  5. 0
    Mohamed Abdelhady ·

    Hi all , I need to ask how to

    Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?

  6. 0
    Nigel Hussey ·

    *

    *

  7. 0
    Zoltan Palffy ·

    this shoud do it Display all

    this shoud do it 

    Display all rowsParameterIsValueHigh Value
      WhereEarly Startis within range ofDDDD+2W
      OrLate Finishis within range ofDDDD+2W
      OrActivity StatusequalsIn Progress
  8. 0
    Habib Hajjaji ·

    Why we are using late Finish

    Why we are using late Finish in this below Filter?????

    WhereEarly Startis within range ofDDDD+2W
      OrLate  Finishis within range ofDDDD+2W
      OrActivity StatusequalsIn Progress
     

    In My Opinion below filter is enough.

    WhereEarly Startis within range ofDDDD+2W
          
      OrActivity StatusequalsIn Progress
  9. 0
    Zoltan Palffy ·

    Hiahab all you did was copy

    Hiahab all you did was copy mine

    use the start and fiinsh dates do not use early and late 

    Display all rows            ParameterIs               Value                HighValue 

    Where               Start is within range of           DD                    DD+2W 

    Or                     Finish is within range of         DD                    DD+2W 

    Or                Activity Status                           equals                 In Progress

  10. 0
    Kathy Castle ·

    To create a look a head

  11. 0
    Zoltan Palffy ·

    qyestion was 2 week not 3 or

    qyestion was 2 week not 3 or 4