Global change resource dates

Anthony PetersMember for 19 years 6 months
Created
1
2
0

Is there any global change parameters that will align resource start/finish to activity start finish. I have about 300 activities that need alligning and need a quick way to do it. When i tried a global change, it would only affect activities OR activity resource assignments, not a mixture?

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    > make sure that calendar

    > make sure that calendar used for the resources is matching with activity calendar.

    > make sure that effective date of Resource units and prices is before the start date of the project.

    >make sure that resource curve used will distribute resources from the beginning through the end of the duration of the activity.

    > Scheudle the project to make sure changes effects.

    >Refresh by keying F5.

     

    Hope this will help.