Tracking Critical Path

Reece BeutelMember for 15 years 8 months
Created
3
2
0

Hi all,

This is my first post on Planning Planet so I'd like to introduce myself. I'm working on a multi high-rise project in Brisbane, QLD, Australia and although I have a few projects under my belt, this is my first job as Project Planner. We use Primavera P6 V7 Project Management here and I am basically required to plan and schedule two programmes - a client-issued programme and a subcontractor-issued programme.

The programme includes procurement, design, construct (substructure and superstructure), fitout and handover. Currently we are mid-way through substructure and I am having some trouble tracking the critical path. Depending on how I relate / lag the foundation piling with bulk excavation and the retention system, the critical path seems to "disappear" until fitout begins. As a remedial fix I have included links to Finish Milestones with finish constraints so that subcontractors still see a critical path on their weekly month-lookahead programme issue. However, I think this is a bit of a bandaid fix, but I can't seem to find any errors in my logic that are causing the critical path to disappear. Can anyone suggest what I can try to get a critical path running through the project? It's obvious what the critical path is on-site, but I want to reflect this in the programme (particularly as we have had a LOT of rain in recent months and EOT's are coming in left right and centre).

Kind regards,

Reece

3 replies

Oldest first
  1. 0
    Andrew Tan ·

    Hi, Your critical path is

    Hi,

    Your critical path is assuming the longest path and not critical activities.

    Link it all the way from the start till the end and make that last activity 1 day later from the rest. It should appear.

    Cheers.

  2. 0
    Rafael Davila ·

    For an interesting view on

    For an interesting view on the subject please follow the link.

    http://www.alphacorporation.com/49R-06.pdf

  3. 0
    Naveen Paladugu ·

    You can go to schedule

    You can go to schedule options & define critical activities as "Total float less than or equal to option". So based on your definition and relationships you could show valid critical path

Log in or join to reply