Same value of Budget Labor Units and Custom Defined Field using global change in P6

Num LockMember for 20 years
Created
6
4
0

Dear All,

Hi, I already have values in my custom defined field "WF". I cannot use global change so my Budget Labor Units will be equal to the values in my custom defined field "WF". Any work around? 

Thank you.

Regards,

Num

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi Num Lock, Please check

    Hi Num Lock,

    Please check your Security Profile assigned to you if you are not a superuser. You might not allowed to edit part or whole of the project data.

     

    Hope this will help.

     

    Regards,

     

    Raymund

  2. 0
    Amit Parmar (PMP) ·

    Hi,Can you please tell me

    Hi,

    Can you please tell me what formula are you using while using global change.

    Regards

    Amit Parmar

    Check out my blog on PrimaveraBlog at http://www.primaverablog.in

  3. 0
    Num Lock ·

    Hi I already changed the

    Hi I already changed the security profiles but still it doesn't work.

  4. 0
    Num Lock ·

    Hi, I simply use 2 global

    Hi, I simply use 2 global change:

    1. Global change 1 (Activities):

    user_number6 = _sc wf

    2. Global change 2 (Activity Resource Assignment):

    Budgeted labor units = user_number6

  5. 0
    Num Lock ·

    Hi, anyone has solution for

    Hi, anyone has solution for this one? Thanks.

  6. 0
    Num Lock ·

    Hi, anyone has solution for

    Hi, anyone has solution for this one? Thanks.