Export Resource/Cost Assignment to Excel format.

Tandyo WinarnoMember for 17 years 3 months
Created
8
2
0

Dear All,

 

Would you please advise me how to export Resource/Cost Assignment shown from Assignment menu on the Directory Bar?

 

 

Thanks

Tandyo

8 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, Select Resources>>> Copy

    Hi,

    Select Resources>>> Copy >>> Paste in excel.

     

    Hope this will help.

     

    Regards,

     

    Raymund

  2. 0
    Tandyo Winarno ·

    Thanks Raymund, I already

    Thanks Raymund,

    I already did, however it works only for resource description shown in the screen shot at upper left while it doesn't work for the resource assignment shown in upper right (resource assignment for every month/day) 

     

     

    Regards,

    Tandyo

  3. 0
    Raymund de Laza ·

    Hi Tandyo, I am using P6 and

    Hi Tandyo,

    I am using P6 and it works well by selecting, copy and paste. In the excel, I can see the loads in time intervals.

     

  4. 0
    Amit Parmar (PMP) ·

    Hi,What all data do you want

    Hi,

    What all data do you want to export from Primavera?

     

    Regards

    Amit Parmar

    Check out my blog on Primavera at http://www.primaverablog.in

  5. 0
    Amit Parmar (PMP) ·

    Hi,You can try exporting data

    Hi,

    You can try exporting data to an excel sheet, using the export function. You can design the template and set the data you want to export based on filters and columns

    Regards

    Amit Parmar

    check out my blog on Primavera at http://www.primaverablog.in

  6. 0
    Tandyo Winarno ·

    Thanks All,   You are right.

    Thanks All,

     

    You are right. It works.

    I tried on other machine (local database) and it works.

    I work in the server database and can not work for such function. 

     

    Thanks

    Tandyo W. 

  7. 0
    Arend Kok ·

    Tandyo,   You can also use

    Tandyo,

     

    You can also use the report wizzard to set up the fields over the time distribution you need and then output the report to a csv file.

     

    Regards,

    Arend.

  8. 0
    Tandyo Winarno ·

    Thanks a lot Arend. I follow

    Thanks a lot Arend.

    I follow your guidance and it works.

     

     

    Regards,
    Tandyo