P6V7 levels resource actual units
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 8 months
- Created
- 1
- 2
0
Hello planners,
on Activity A, Original Duration 5 days, Resource 1 is working 8 hour/day
Activity Actual Start is Monday and Actual Duration 2 days
Update Progress on Tuesday night shows Resource 1 Actual Units = 16h, 8 on Monday and 8 on Tuesday
On Wednesday night, I schedule the project to show that there was no work at all on Activity A on Wednesday; on the Activity Usage Spreadsheet, P6 shows that Resource 1 worked 5,33 hours per day during 3 days, when I want to read 8 hours per day during 2 days and 0 on Wednesday
I cannot find where the setup is
Please somebody help!
All the best,
Alexandre