Hi guys,

I've been asked how you can change the colour of the spotlight from yellow to something more desirable to the client (I know, on a list of priorities...)

With all the formatting options I would be surprised if this is not possible but cannot find where I need to be, can anyone help?

Regards,

Paul

1 reply

Oldest first
  1. 0
    Neal Walsh ·

    Hi Paul, AFAIK I don't think

    Hi Paul,

     

    AFAIK I don't think it's possible to change the spotlight colour.....it's fixed at yellow.

    However, why dont you just use a curtain instead? This highlights any specific area and you can chose any colour you like, the only downside being it's only viewable on the Gantt chart.

    Hope this helps?

    Walshy