Updating With Resource-Costs for Corps

Emily GroverMember for 15 years 7 months
Created
5
3
0

I have a P6v7 schedule created with the cost for each activity as a resource (rather than Expense, so that it can be used to create an SDEF for QCS input). The 'calculate costs' and 'auto compute' ticky-boxes are ticked. When I update the activity percentage (physical), both simply in-progress or complete, it clears the dollars out of the budgeted cost in the resource (setting it to $0).

 

I understand that P6 is unequated (dollars and durations will not run off the same entered percentage) so I already know I'll need to enter each update twice. But I'd really like to have the budgeted total stick around so I know how much it is without flipping back and forth to a previous schedule. How do I keep the resource-loaded budget from clearing when I update?

 

- ES

5 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, Please check the settings

    Hi,

    Please check the settings of your Earned Value Calculation on the Admin Preferences.

    Hope this will help.

     

    Regards,

  2. 0
    Emily Grover ·

    Raymund, thanks for the

    Raymund, thanks for the suggestion!

    I've looked through those options and I'm not seeing what ought to be different. Just in case, I tried all three options down in the bottom-most area and the budgets continued to clear. Is there somewhere else I should be looking / changing?

    Thanks again!

    - EG

  3. 0
    Raymund de Laza ·

    Hi Emily, I can't figure out

    Hi Emily,

    I can't figure out what exactly the problem happens with your Project.

    APMU Budgeted Cost shall be intact even the project is updated.

    Can you share a screen shot of your project?

     

    Regards,

  4. 0
    Emily Grover ·

    Raymund:Here it is before:

    Raymund:

    Here it is before:

    After I mark the activity 'completed' in the drop-down box for Activity Status, the following is the result. No other changes were made to the activity. Note the 'Budgeted Nonlabor Cost'.

    Hopefully that helps clear it up!

    - EG

  5. 0
    Raymund de Laza ·

    Emily, I'm sorry was not able

    Emily,

    I'm sorry was not able to get a solution for the prob. It's rare.

    I doubt there might be mistakes while assigning the resources. Try removing the resource and reload, recalculate.

    Or maybe try having a new sample project and do the exercise.

     

    Regards,