Plant Shutdown - Resource Allocation
- Created
- 3
- 2
Hi All:
I am involved in a shutdown project and where have encountered the case detailed below
- The Activity Duration is 132Hrs (12Hrs x 11 shifts) & each shift is different with different mix of resource requirements.
- Please note that I have delinked the option to calculate activity duration basing on resource assignments (Edit-User preferences-Calculations)
- After the resources are assigned as below as per the respective calendars, I find that the resource budgeted/planned hours are not being allocated shift wise rather it is distributed to the entire duration of the Activity from start to finish.
- Kindly advise how to solve this case.
|
Time scale (Day/Shift) |
Start 5/05/2011 |
6/05/2011 |
7/05/2011 | |||
|
Project Calender: 2 Shifts – Day (6am-6pm) & Night (6pm-6am) |
Day 5 |
Night 5 |
Day 6 |
Night 6 |
Day 7 |
Night 7 |
|
Activity 1 – Resources Required |
F22+F23+R6+R7 |
F22+F23+TR3+BM7 |
F22+F23+R6+R7 |
TR2+BM1 |
TR2+BM1 |
|
|
Resource Hours Budgeted |
48hrs (4x12Hrs) |
0 |
48hrs (4x12Hrs) |
24hrs (2x12Hrs) |
24hrs (2x12Hrs) |
0 |
|
Time scale (Day/Shift) |
8/05/2011 |
9/05/2011 |
Finish 10/05/2011 | |||
|
Project Calender: 2 Shifts – Day (6am-6pm) & Night (6pm-6am) |
Day 8 |
Night 8 |
Day 9 |
Day 8 |
Night 8 |
Day 9 |
|
Activity 1 – Resources Required |
NDT |
C1+R6 |
NDT |
C1+R6 |
||
|
Resource Hours Budgeted |
12hrs (1x12Hrs) |
24hrs (2x12Hrs) |
0 |
12hrs (1x12Hrs) |
24hrs (2x12Hrs) |
0 |
Resources Legend: F - Fitter, R - Rigger TR - Trade Person, BM - Boiler Maker, NDT - Non-destructive Testing Team, C – Crane
Resources Calender: 1) Day Shift (6am – 6pm) 2) Night Shift (6pm – 6am)
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?