Kumar
you are not doing somenting correctly once you put in an actual date there is no longer an Early start date. The actual start date over rides the start date becaus eit is an actual.
What you are talking about is the start of the activity for the REMAINDER of the activity.
if you have an activity that has 10 days as the original duraiton and you have an actual start and you say this activity is 50% complete then the remaining duration is 5 days. So the earlies that the raming 5 days of work can being is at the data date.
If this activity has a predecessor that ha snot bene completed then the remaing 5 days can not begin unitl ist precedessor has been comepleted.
You need to understanbd how dates are calculated
the early dates are calcuated during the forward pass and goes forward in time. The forward pass begins with the start of the project or the data date this gives you the early start and early fininsh dates.
the laste dates are claculted during the backwardpass and start it the end of the project or the projetc must finish by date and goes backward in time to give you the late start and late fininsh dates.
the difference between the late dates and the early date is the float.