How can i refelect the no of deliverable in Primavera
In the Open Standard
Kumar BaijuMember for 15 years 8 months
- Created
- 2
- 2
0
Hi all
I am preparing an engineering Schedule. in which suppose any activty such Detail drawing of Compressor will contain 20 A1 size drawing. How can i refelect this in schedule.
ACTIVITY Duration Resource No Of deliverable Start Finish
Detail ... 60 Days Asst manager Eqp 20 1-Jul-11 31-Aug-11
Now i want that if i generate report that hhow many deliverable will be deliver in Jul Result will be 10 (10 for Jul) and 10 for Aug.
Thanks\\