critical path and loop

Moh HamMember for 15 years 7 months
Created
1
4
0

Hi,

I'm beginner in primavera; I just want to know how can I discover if there is any loop on the Critical path

 

Thank you

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    Primavera will automatically

    Primavera will automatically give you an error message detailing any logical loops in the project when you try to schedule it.

     