Skip to content

How to assign actual cost rate in the update ?

Jehad KharrazMember for 15 years 6 months
Created
0
2
0

Hi,

This is my first post here in Planning Planet .. it's a question and i hope get ur help ..

.......................................................................................................................

If i want to made an update for my project .. how I can assign actual cost rate for the materials ..

here, my question, not actual material cost, but actual rate..

for example, suppose I have a concrete material resource which have a cost of 150 $/M3

and when I doing the update I would like to change to the actual cost of 200 $/M3 .. then how to doing this ??

..........................................................................................................................

hope to receive your answer quickly ..

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?