Open Link for an activity

Mangesh KhuspeMember for 19 years 6 months
Created
7
1
0

Dear All,

 

What are the steps to check for an activty which does not have any sucessor?

 

 

With Regards,

 

Mangesh

7 replies

Oldest first
  1. 0
    Rafael Davila ·

    Just apply a filter for

    Just apply a filter for Activities without Successors/Predecessors it would be too primitive to run the schedule to get a report, same as scrolling all activities, especially if a schedule of thousands of activities.

    The following screen display how Spider provides for such filters you can apply to the whole project or a selection of WBS phases. Look for such equivalent filter in P6. If not pre-defined you shall define it yourself. After this it shall always be available at a single click of the mouse and error proof, no single activity missed.

    Open Ends

  2. 0
    Mangesh Khuspe ·

    its does not work out in p6

    its does not work out in p6

  3. 0
    Gary Whitehead ·

    To Quote Rafael: "If not

    To Quote Rafael:

    "If not pre-defined you shall define it yourself"

     

    Create a filter where successors = blank

  4. 0
    Mangesh Khuspe ·

    Thanks Gary and Rafael , It

     

    Thanks Gary and Rafael ,

     

    It worked

     

    With Regards,

     

    Mangesh 

  5. 0
    Mangesh Khuspe ·

    Thanks Gary and Rafael , It

     

    Thanks Gary and Rafael ,

     

    It worked

     

    With Regards,

     

    Mangesh 

  6. 0
    Rafael Davila ·

    Mangesh, I always try to keep

    Mangesh,

    I always try to keep an up to date Template Job I use to store all my favorite Layouts, filters, formulas, reports etc then I can use it as a template on new jobs or as a reference to transfer my layouts, filters, formulas, reports ... easier than searching all over.

    This was an easy filter but sometimes even the most basic filter can be complex, like a look-ahead filter for example, same goes for reports.

    Best regards,

    Rafael

  7. 0
    Mangesh Khuspe ·

    Dear Rafael, Thanks a lot for

    Dear Rafael,

     

    Thanks a lot for the valuable suggestion, will definitaley impliment this now and in future also. I just shifted to P6 after a break of 3 years ( I used p3 before that). Lots of changes, after trying for different fields i again moved into planning and scheduling as it gives me utmost pleasure. 

    Will opt for PSP now.

     

    With Regards,

     

    Mangesh Khuspe

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?