Skip to content

Acvity Complete and Activity Step Complete

Marcus LoveMember for 16 years 3 months
Created
0
2
0

Hello Fellow Planners,

 

I was wondering if the activity steps are linked to activity complete at all?

 

In order to clarify my question, I would like to give an example:

If my activity has 3 steps (same weight assumed-> 0,33) and I check one step as completed, the activity has a progrss of 33%. Will this progress be transferred to the activity complete (status tab in activity details), as well? also, does this transfer depend on the activity percenet complete Type?

 

I have tried to accomplish the challenge mentioned above, but it seems that I have to transfer the activity step complete % to the activity % complete field manually.

I would be glad to hear from you!

Thank you very much!

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?