Acvity Complete and Activity Step Complete
- Created
- 2
- 1
Hello Fellow Planners,
I was wondering if the activity steps are linked to activity complete at all?
In order to clarify my question, I would like to give an example:
If my activity has 3 steps (same weight assumed-> 0,33) and I check one step as completed, the activity has a progrss of 33%. Will this progress be transferred to the activity complete (status tab in activity details), as well? also, does this transfer depend on the activity percenet complete Type?
I have tried to accomplish the challenge mentioned above, but it seems that I have to transfer the activity step complete % to the activity % complete field manually.
I would be glad to hear from you!
Thank you very much!
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?