Manhours and BOQ (Resource) Assignment

Syed AliMember for 18 years 10 months
Created
7
6
0

Dear All,

Manhours and Unit (Resource) Assignment-in P6 Schedule

I am in process of developing construction schedule (as I will be migrating from P3 to P6) need help on the following:

  1. How can I assign budgeted manhours to activities (Direct+Indierct)
  2. Budgeted Quantity of activity (MTO)
  3. Creation of Calendars with holidays as site will be on rotation 10days works 4days off.

Subsequently Can I generate S curve for above separately?

Can I use earned value of direct manhours to update weekly S curve?

Thanks & regards,

Ali

7 replies

Oldest first
  1. 0
    Safak Vural ·

    Ali,The subjects you are

    Ali,

    The subjects you are asking is nearly all course content of PM-102. The course book is hundreds pages.

    If you are migrating from P3 you need to study because; Duration Types, % Types, Baselining, Export&Import and reporting (Especially reporting) are quite different and complicated from P3 in first glance.

    My recommendation is take at least PM-102 (3 day course) in order to familiarize with software.

    Regards,

    Safak

     

     

  2. 0
    Syed Ali ·

    Thanks Safak, I have already

    Thanks Safak, I have already gone through P6 102 & 106 courses.

    This query popped up because while I assign manhours & qty the default unit/time and budget unit time shown in % is this ok?

    Thanks,

    Ali

  3. 0
    Safak Vural ·

    Ali,As far as I understand

     

    Ali,

    As far as I understand you want to have basic setup as P3:

    - Actual to date = % * BQ

    - Link remaining duration with % complete.

    So when you enter % of activities after scheduling you can have actual values equals to earned values. Also having single earned value / Baseline S-Curves.

    You should use Fixed Duration & Units and also make Duration % same as Units % (or you can update Actual QTY as BQ * % Duration). This will give you earned values and zero variance remaining quantities that you can have S-Curves projections in earned values and monitor SV. Be informed that this way you cannot monitor CV.

    I hope I understand your need and help it.

    Regards,

    Safak

  4. 0
    Syed Ali ·

    Thanks Safak, More response

    Thanks Safak, More response please.

    Regards,

    Ali

  5. 0
    Safak Vural ·

    Ali,I think I do not

     

    Ali,

    I think I do not understand your questions. I am not thinking that you are asking about; “from which menus or items you are going to assign resources change calendars and export loadings at P6”.

    Sorry I cannot help you.

    Regards,

    Safak

  6. 0
    Rafael Davila ·

    Look for Converting P3

    Look for Converting P3 Projects to P6 chapter in the following reference, it might be of help.

    In particular page 123: Verify each resource’s unit of measure in P3 and how it will convert to the PM module.

    http://download.oracle.com/docs/cd/E16281_01/Moving_From_P3_to_P6/MovingfromP3toP6.pdf

  7. 0
    Syed Ali ·

    Thank you. My question was

    Thank you. My question was where to assign them in P6 under different resource category of same type of resource i.e. labor I have to assign budgeted manhours and quantity of each activity. Later extract progress and earned value & quantity.

     

    Regards,