Manhours and BOQ (Resource) Assignment
In the Open Standard
Syed AliMember for 18 years 10 months
- Created
- 7
- 6
0
Dear All,
Manhours and Unit (Resource) Assignment-in P6 Schedule
I am in process of developing construction schedule (as I will be migrating from P3 to P6) need help on the following:
- How can I assign budgeted manhours to activities (Direct+Indierct)
- Budgeted Quantity of activity (MTO)
- Creation of Calendars with holidays as site will be on rotation 10days works 4days off.
Subsequently Can I generate S curve for above separately?
Can I use earned value of direct manhours to update weekly S curve?
Thanks & regards,
Ali