group total function

Ozgur KMember for 16 years
Created
2
2
0

Hi,

I couldn't find a solution regarding the below issue.

I want to show the group total of the data which i organized. After click to this option somehow Primavera calculated the OD as 254 days. 

Start Date:1 Oct 10 A

Finish Date: 13 Jun 11

Data Date: 31 Dec 10

OD=254 , RD=165

Calendar 7 Daywork

When i created a new project that contains only 3 activities which has the same situation (dates, calendar, DD date), Primavera calculated the OD as 256.

What is the difference?

Any help will be appreciated.

Özgür

2 replies

Oldest first
  1. 0
    Shareef Abdul Azeez ·

    Group totals are calculated

    Group totals are calculated using Global Calendars ---Not Project Calendars.

  2. 0
    Ozgur K ·

    thanks but Global Calendar is

    thanks but Global Calendar is same, 7 daywork.