Hi friends,

Anybody please explain how to print a report on project % progress based on manpower

how can we calculate the sv based on manpower

 

Thanks & Regards

Sunil Babu

5 replies

Oldest first
  1. 0
    Amro Ahmed ·

    From Activity Usage

    From Activity Usage Profile

    then graph - Options-calculate average -divide intervals total by (put total amount to get %)

  2. 0
    Sunil Babu ·

    Hi Amro,Thanks for your

    Hi Amro,

    Thanks for your help.

    Sunil Babu

  3. 0
    Amro Ahmed ·

    welcome any

    welcome any time sunil

    eng_amrelsaied@hotmail.com

  4. 0
    Sunil Babu ·

    Hi friends,I have little

    Hi friends,

    I have little doubts in making s-curve by the following steps

    1. assign a common resource to all activities

    2. est % wt to all activities

    3. top down estimation method

    4.monthly cumulative budget

    5. transfer to excel sheet

    can anybody help me on these things or send any pdf regarding this

    With regards

    Sunil Babu

  5. 0
    Sunil Babu ·

    Hi friends,Anybody please

    Hi friends,

    Anybody please explain how to print a report on project % progress based on manpower

    how can we calculate the sv based on manpower

     

    Thanks & Regards

    Sunil Babu