Activity id changa With Global Change

Amro AhmedMember for 17 years 9 months
Created
4
2
0

If i have schedule 3000 activities and activity id :A1000 then A1010.....ETC

i want to chnge foudation activities group to FN 1000..........

Structural to STR1000 ..........

HOW do with global changes?

4 replies

Oldest first
  1. 0
    Peter Gable ·

    Hi Amro I have a global

    Hi Amro

    I have a global change definition that can do this for you.

    Please e-mail me and I will gladly send it to you.

    Peter Gable

    P6 EPPM Specialist

    www.rpc.uk.com

    peter.gable@rpc.uk.com

  2. 0
    Amro Ahmed ·

    Thank you peter for your

    Thank you peter for your response,

    my email: eng_amrelsaied@hotmail.com

  3. 0
    Peter Gable ·

    I have sent you an

    I have sent you an e-mail.

    This tip will be apppearing on our Knowledge Zone very soon.

    http://www.rpc.uk.com/pages.php?sectionid=36&categoryid=114

     

    Kind regards

    Peter

  4. 0
    Peter Gable ·

    I have sent you an

    I have sent you an e-mail.

    This tip will be apppearing on our Knowledge Zone very soon.

    http://www.rpc.uk.com/pages.php?sectionid=36&categoryid=114

     

    Kind regards

    Peter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?