Resource report for day by day
In the Open Standard
Mangesh KhuspeMember for 19 years 6 months
- Created
- 4
- 3
0
Dear All,
For my project, we want to know, how many no of columns we would be casting daily. to solve this i created a resource named as Columns and assigned it to the activity. I counted the no of columns on each floor and then assigned the nos to the activity. now can anybody tell me how to get this printed on daily basis for entire project. P6 gives for monthly basis but i want it for daily.
4 replies