Skip to content

Resource report for day by day

Mangesh KhuspeMember for 19 years 6 months
Created
4
3
0

Dear All,

For my project, we want to know, how many no of columns we would be casting daily. to solve this i created a resource named as Columns and assigned it to the activity. I counted the no of columns on each floor and then assigned the nos to the activity. now can anybody tell me how to get this printed on daily basis for entire project. P6 gives for monthly basis but i want it for daily.

4 replies

Oldest first
  1. 0
    Anoon Iimos ·

    you can make your timescale

    you can make your timescale on a daily basis, but I supposed your approach is wrong, it will depend on how you structure your activities

  2. 0
    Mangesh Khuspe ·

    Dear Anoon,Thanks for the

    Dear Anoon,

    Thanks for the reply, I didnt understand what you want to say. can you please explain?.

    This is the simplest method for me as it will give the daily usage of resource.

     

     

     

     

     

  3. 0
    Anoon Iimos ·

    If you are working on a high

    If you are working on a high rise building, the columns will be dependent on the casting of the floors, why don't you just count directly from the drawings?

  4. 0
    Mangesh Khuspe ·

    Dear Anoon, There is some

    Dear Anoon,

     

    There is some confusion going on ( I suppose). I have counted the No of Columns from the drawing and added this as a resource to Column activity in the program. Now the Program gives resource usage for the duration of activity. i want to know the no of columns which are to be cast on daily basis. which i have tried through the Report editor, but failed to do so.

    I hope i am clear now.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?