Loading Budgets , Earned Value

Barry FullartonMember for 17 years 9 months
Created
3
1
0

Guys , please we want to implement a simple Earned Value system here, I want to take budgets from the BOQ and load it at a WBS level and not at an activity level we want to measure our Earned Value at this level , However how or where does one input these values into P6

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Your best bet is probably to

    Your best bet is probably to create a summary LOE task per wbs element you want to load, and link it to all activities within that element.

     

    You'll have to think carefully about how you measure progress, though.

  2. 0
    Niles Luo ·

    Hi,     maybe you can do as

    Hi,

        maybe you can do as the following steps.

        Create an WBS type activity for each WBS that you want to Calculate the Earned Value

         Each WBS type activities' progress should be set as physical. 

         Load budget for each WBS type activity, then save as baseline.

        Each datadate, the cost and progress should be updated for each WBS type activity.

        If you have done the above step, you could do the EVA

    Good luck

  3. 0
    Cutepriya Civil ·

    anybody have earned value

    anybody have earned value analysis reports....

     

    can mail to : cutepriya.ap@gmail.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?