Importing SDEF from P6 to QCS, Feature of Work errors
- Created
- 7
- 3
I have recently switched over from p3 to p6 and was having no issues with importing to QCS.
I just imported the sdef file from p6 for the first time into QCS and it messed up all of my features of work. In p6 i have the activity code FOW, then the code value for each feature of work, then it has the description of the code value under description. All the code values are the same i have always had but now when i imported the sdef file QCS has added another feature of work that is equal to the description not the code value and associated all related activities to the added value.
So all my original FOW's still have all my manually entered QCS info associated with it (preps, initials, aha's) but all the activities are now assigned to the new FOW which is equal to the description.
Do i just have something wrong in my settings which caused the sdef file to tell QCS to add another FOW and reassign all the activities? Or is there a bigger issue?
Thanks for any input.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?