Primavera Calendar P6

Muthukumaru SenthuranMember for 15 years 5 months
Created
2
2
0

I have some problem...

In the same  project ,Activity "A" can be carried out only day shift ( 8 hrs), and Activity "B" to be carried out day and night shift ( 24hours).

 

Please let me know how to assign the different calendar for the same project in Primavera P6

 

Senthuran

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    To create or ammend different

    To create or ammend different calendars, go to Enterpise > Calendars

     

    Assigning a calendar to a particular activity can be done in the general tab of the activity details window

     

    NB: When using different calendars on a project, it is important to understand which calendar will be used when calculating lags. To do this, got to tools > schedule > options.

  2. 0
    Mike Testro ·

    Hi Muthukumaru Another point

    Hi Muthukumaru

    Another point to remember is that different calendars will affect the critical path - for instance:

    If your 24hr task ends in the middle of a hoilday period and is linked to an 8hr task that starts after the holiday the gap will register as float.

    Best regards

    Mike Testro