Logic link question
In the Open Standard
Thomas NicholsonMember for 20 years
- Created
- 3
- 3
0
Hi all,
I wonder if someone could help me.
I have several activities that start at the same time and one that starts later
A 2-12-11
B 2-12-11
C 2-12-11
D 10-12-11
I want them all to link to activity E so that E starts on the 2-12-11 however when I use a SS link it ignores the early date and starts on the 10-12-11 instead. Is there a way of linking all the activities together and get E to start 2-12-11?
thanks in advance,
Thom
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
