Resourses distribution with given daywise for one activity
- Created
- 12
- 3
Hii,
I am using P6.7 version. Currently i am planning for Integrated cement plant project. The issue which i am facing now is...
I have created the 18.5 month Schedule with assigning of resouses. I am one query regarding is that. Suppose I have created One activity of say duration 20 days. Now with respect to this activitity i have assigned 4-5 resouses say (Excavator, dumper, helper and supervisor etc).
Now the point is i want to distribute Supervisor and helper for the whole duration of activity (i.e. 20 days). and at the same time Excavator i want to use for starting 15 days (not being used for last 5 days) and Dumper i want to use for last 10 days (not being used for starting 10 days).
So, can you help me out in this accout that how i would assign the resourses for one activitiy (20 days) with above distribution of resorses by given day wise.
Please tell the process..
Rgds,
Pankaj
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?