Push to move away from WBS to Activity Codes

Martin SelleyMember for 20 years 7 months
Created
4
2
0

Hii,

Anyone gettibng pressure from Company to move away from WBS to using solely Activity Codes?

I know primavera/oracle have been pushing this but don't know how far this has gone.

Usually non-planners push this type of change.

4 replies

Oldest first
  1. 0
    Sam . ·

    No pressure at my end. Yet.

    No pressure at my end. Yet. Seems to be common practice to use WBS elements.

  2. 0
    Jonas Ray Puig ·

    Hi Martin,No pressure my end

    Hi Martin,

    No pressure my end as well.  May I ask what pressure seems to arise your end in using Activity Codes?

    Check this out anyway, might help:

    http://www.youtube.com/watch?v=NNyaKBzr5Ak

    Regards,

    JRP

  3. 0
    Mimoune Djouallah ·

    you can easily map your wbs

    you can easily map your wbs to use activity code instead, just excel and the use of the sdk

  4. 0
    Dennis Hanks ·

    [Stepping on my soap box]For

    [Stepping on my soap box]

    For me, the value lies in linking the schedule to the estimate/budget.  If your estimate/budget is not organized by project WBS, there is little additional value over activity codes - except that P6 seems to really like using a WBS.

    No suggestion that any schedule not be fully integrated - resource loaded - with Estimating and Accounting.  In other words, IMHO, all schedules should be resource loaded and therefore rely on a fully developed WBS - use activity codes whenever the need arises.  It is not an either/or, but rather what is appropriate.  

    All schedules should be resource loaded from a source external to the planner/scheduler and this source be cited in the Schedule Basis.

    [now stepping down from my soap box]