Setting Resource start and finish to equal activity start and finish

Nathan BurmanMember for 18 years 10 months
Created
3
2
0

Hi all,

 

Does anyone know a quick way of setting resource start and finish dates to match activity start and finish dates?

I've tried both global change and exporting as an excel spreadsheet but can't find the 'Activity Start' field.  I've found that column in Resource Assignments view and it gives me the dates I'd expect but I can reference it anywhere in either Global Change or Excel fields.

 

Any help would be much appreciated.

 

Thanks,

 

Nathan

3 replies

Oldest first
  1. 0
    Anoon Iimos ·

    I'm not sure if I understand

    I'm not sure if I understand you correctly, but how about using exactly the same calendars for both activities and resources?

  2. 0
    Nathan Burman ·

    For clarification the

    For clarification the situation is this:

    In the past for various reasons the start and/or finish dates of resources assigned to activities have been modified manually so that in many cases the dates do not match the activity start and finish dates.

    I am looking for a quick way to revert all assigned resources on the programme back to the original default dates which match the activity dates when the resource is assigned.

    Thanks,

    Nathan

  3. 0
    Anoon Iimos ·

    still unclear, how about

    still unclear, how about restoring your baseline?

    have you levelled your resources manually or automatically? - I believe Rafael is the expert on this one.

    are you using different calendars? how many?

    For example: You use different calendars for activities and resources; and then you level your resources automatically, what happens? or what is the result?

Log in or join to reply