Program update at P6
In the Open Standard
Wilfredo BarbacenaMember for 17 years 5 months
- Created
- 5
- 1
0
Hi,
Need some help here, have revised/rebaseline an existing plan and performed a program update. The first thing I have noticed that some of the activity finished date have moved, where it supposed not. Have tried everything but still it's changing, would gladly appreciate any advice.
Regards,
Willy
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?