Program update at P6

Wilfredo BarbacenaMember for 17 years 5 months
Created
5
1
0

Hi,

Need some help here, have revised/rebaseline an existing plan and performed a program update. The first thing I have noticed that some of the activity finished date have moved, where it supposed not. Have tried everything but still it's changing, would gladly appreciate any advice.

Regards,

Willy

5 replies

Oldest first
  1. 0
    Ferdinand U. ·

    changing after scheduling

    changing after scheduling F9?

    or you are talking about baseline/planned dates?

  2. 0
    Wilfredo Barbacena ·

    I am using the update

    I am using the update progress, not the F9 or manual update. Yes, I am referring to the planned dates.

  3. 0
    James Soto ·

    I am trying to update my

     

    I am trying to update my schedule, can someone please help? I need to update to 100 % complete for a few tasks.

  4. 0
    James Soto ·

    yes, I tried to go to update

    yes, I tried to go to update the physical percent complete, i tried to go to

    activities

    dependents

    % complete,

    I am in trouble here,

  5. 0
    James Soto ·

    How do I update the base

    How do I update the base line?

Log in or join to reply