Resource Loading - Tabular & Graphics

Ariel MalibiranMember for 17 years 7 months
Created
1
2
0

Guys help please!

Can anyone advise me on how to generate the Tabular Resource Loading and Graphical Resource Loading in P6... I am able to do it in P3 but don't know how to do it in P6. I can only see the Graphical Loading of Resources in the Resource Usage Profile but i have no idea on how to get it out...Or if anyone has a predefined template/report format for these reports, I shall be very thankfull if you could extend it to me..

Thanks

 

Ariel

1 reply

Oldest first
  1. 0
    Mimoune Djouallah ·

    It is possible to create

     It is possible to create Custom Reports using the Integration API, SDK or the Enterprise Reporting Database. However, this would require programming knowledge and/or 3rd party applications in order to accomplish this.

    2.  Export the Report to Excel and use Excel features to get the Report to show the X and Y axis flipped (i.e. A Macro can be created to do this, which requires programming knowledge as well).

Log in or join to reply