Guys I need some help please!

How to delete all the resource assignment for all activities using Global Chnage (P6)...

 

Thanks,

Ariel

3 replies

Oldest first
  1. 0
    Rafael Davila ·

    Why not delete all resources

    Why not delete all resources from resource dictionary?

  2. 0
    Ariel Malibiran ·

    I can't delete the resources

    I can't delete the resources in the dictionary because I still be using it. The quantities have been changed in the assigned resources and some of it are no longer applicable. So, I have to remove all the assigned resources in each activities to make sure that next time i reload the resources it will be correct.

     

    Thanks,

     

    Ariel

  3. 0
    Ariel Malibiran ·

    Assigned resources to

    Assigned resources to activities can be removed from each activities at the same time without using Global Change. Simply display the Resources column in the current layout, select all the activities to highlight all the activities you want to remove the resources and then select one activity with resources-Resource Assignment dialogue box shall apear, in that dialogue box, choose the resources you want to remove and choose REMOVE(icon with red X mark)...This will remove the assigned resources in the activities but not in the dictionary.

     

    Cheers!

     

    Ariel