Hi everyone!

Need some help pls..I have loaded my resources (Labor and NonLabor) in the schedule using the export/import functions. The odd is after the importing of resources, the Resource Type for all the NonLabor resources I have imported were changed to Labor although it were NonLabor in the spreadsheet I have used during the import.

Thanks,

 

Ariel

3 replies

Oldest first
  1. 0
    Pinan T. ·

    hi arielwhich p6 version did

    hi ariel

    which p6 version did you use?

    6.0 or 6.1 bug i think

    export the project to xer then import as new project will solve it in 6.1

    6.2 and later version solved this problem

  2. 0
    Ariel Malibiran ·

    Mr. Pinan T.   I think im

    Mr. Pinan T.

     

    I think im using P6.0. Not so sure, coz I just got it from my friend. You're right, exporting and importing the schedule in XER solved the inconsistencies. By the way, how can I know exactly the version of P6 I am using? Can't find it the properties of P6.

     

    Thanks again,

     

    Ariel

  3. 0
    Pinan T. ·

    In the menu, select Help then

    In the menu, select Help then click about primavera

    you will see the release version

    or from your exported xer you can open it in notepad then you can check it if 6.0.0.0 means p6 version 6