Problem in progress override between p3 and p6

Jehad Aldaoud PMP, PMI-SPMember for 16 years
Created
9
1
0

dear planner

i faced problem when i make schedule when i choose progress override in p3 i get result, but when i convert the schedule to p6.7 and make schedule with choose progress override i get different result, i don't know why the result different? and how can imake it the same ??

 

please advice 

9 replies

Oldest first
  1. 0
    Jehad Aldaoud PMP, PMI-SP ·

    any one can help me in this

    any one can help me in this problem ????????????

  2. 0
    Gary Whitehead ·

    What happens when you

    What happens when you schedule both using retained logic?

    When you get different results, what different results do you get?

    do these affect completed activities, in progress, or planned?

    can you see any pattern with affected activity types, calendars, constraints, resources or relationships?

    Do you have out of sequence working?

  3. 0
    Jehad Aldaoud PMP, PMI-SP ·

    Dear Gary  The reason that

     

    Dear Gary 
     
    The reason that forced me to schedule using project override was when i made schedule using retained logic there was out o sequence between the activities ( rebar activity finish after formwork activity in walls ) 
     
    When i made schedule using project override on p3 the problem of out of sequence solved but when i converter it to p6 the problem didn't solved. 
  4. 0
    Haitham Khaireldin ·

    Jihad,Its not a good

    Jihad,

    Its not a good idea/practice to use progress override to overcome out of sequence activities. You should change the sequence yourself.

    Regards,

    Haitham.

  5. 0
    Jehad Aldaoud PMP, PMI-SP ·

    but also it's not good idea

    but also it's not good idea change sequence of work every update, because it will effect in our rights to prepare claim in the furture

  6. 0
    Haitham Khaireldin ·

    Hmmm...now you're confused

    Hmmm...now you're confused about the whole idea

    When I said you should change the sequence yourself, I did not mean that you should change the sequence in favor of the Employer's risk. You should be able to differentiate between your delays and the Employer's ones.

    And sometimes there is no delay involved. It is just a change in sequence than that was originally planned.

  7. 0
    Jehad Aldaoud PMP, PMI-SP ·

    Thank you for your

     

    Thank you for your clarification, but I need how can i solve th problem that i face it now 
     
    Note : out of sequence is result from relationship of crews that  i was planned to use them in the construction
  8. 0
    Haitham Khaireldin ·

    Most of the problems arise

    Most of the problems arise from p3 to p6 conversion are calendars problems.

    So check that calendars and working hours match those in p3

  9. 0
    Jehad Aldaoud PMP, PMI-SP ·

    Thank you for your reply, I

    Thank you for your reply, I check the calendar in P3 and P6 it was the same. any other idea