Hi all,

I'm sure this is a basic problem, but I'm going nuts here. 

I've got a basic level 1 schedule. No logic or anything, just start constraints and durations.

A couple of activities have already started (and the Started check box has been checked accordingly).

Problem: when I change the Data Date the finish date changes (when I wanted it to remain the same). E.g. Activity start date 1st of July, data date 5th of July, finish date 20th of July, 7 day working calendar. Then when I re-schedule witha new data date of 8th of July, finish date now changes to 23rd of July.

Note: Duration type: "Fixed Duration & Units". % Completion Type: "Physical".

I've tried various Duration and completion types combinations, but no success.

Please help! Many thanks.

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi George If the percentage

    Hi George

    If the percentage complete is less than what would have been anticipated at the data date then the end date will move.

    For instance if you have used up 20% of the time but only done 10% of the work then you are behind schedule and the end date will show it.

    If you have the option of using a jagged data line then the end date should not move.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    George,   It sounds like you

    George,

     

    It sounds like you are not ammendign either %age complete or remaining duration when you reschedule to a later date? If so, essentially you are telling the software that zero progress has been made in this period, so you should expect the finish date to slip.

    If all you want to do is move the data without having any effect on the schedule then go to tools, update progress. This will let you tell the software to assume progress has been preciesely as planned in the period.

  3. 0
    Ronald Winter ·

    George,   I am not clear why

    George,

     

    I am not clear why anyone would want to pay $3,000 for Bar Chart Software, but your answer is simple.  Simply use Progress Spotlight and Update Progress to move the Data Date.  (I never thought that I would ever recommend this to someone!)

  4. 0
    John Sims ·

    Hi George, I think this is

    Hi George,

    I think this is happening as some of the others said, you need to update the progress on the activity, if your activity hasnt progressed as much as it should of done then the planned finish date will move accordinally.

    Have you baselined the project? if so you can set the BL1 Start and Finish dates as columns and add a primary baseline line bar and you will see the original dates compared to any slippage, you will then know which activities you need to accelerate to make my your project finish on time.

    Hope that helps.

  5. 0
    Jash Sales ·

    Hi George, If you want to

    Hi George,

    If you want to remain your finish date while your activity is in progress, just assign expected finish date equal to your finish date. Your finish date will not move until your data date is later than your finish date.

     

    Cheers