Showing a resource limit

Martyn CoatesMember for 19 years 2 months
Created
3
3
0

I have a plan which is loaded with man hours, however I can only fit a certain number of men on board the vessel so I want to show a limit on the number of hours in any one day.

 

Can anyone tell me how to set a limit.

 

I know you can do this on each resource to show a limit on a particular resource but I just want an overall limit and then show the overallication.

 

This is to help a planning session to level the plan.

 

cheers

3 replies

Oldest first
  1. 0
    Dieter Wambach ·

    Hi MartynI would appreciate

    Hi Martyn

    I would appreciate this feature as well.

    If you don't yet use roles, you can you the role's limit which can be independent from the sum of the resources' limit - User Preferences --> Resource Analysis. Automatically resources are assigned with their primary role to tasks.

    If you are working with roles you'll assign the resources with a special role to your tasks. Later on you'll check for this special roles.

     

    Good luck!

    Dieter

     

  2. 0
    Martyn Coates ·

    Hi and thanks for the reply

    Hi and thanks for the reply but it doesnt seem to work.

     

    I added all the resources as required as usual and created a role. I added all resources to that role.

     

    I can see the custom role limit on the user preferences but not sure where to set this limit????

    On the resource usage profile options there isnt a setting to put in any limits etc....

    This is a basic need and I'm sure i have done this before in P3 & P5

     

    any help appreciated

  3. 0
    Dieter Wambach ·

    Martyn I'm not quite sure

    Martyn

     

    I'm not quite sure what you did.

     

    Assign a limit to a role: Enterprise --> Roles --> Tab "limits" - equivalent to the resource

    Watch the assignments: View Activities --> Details --> Tab resource --> column Roles. Is it your role.

    Watch the limit: Resource Usage Profile: Show roles, with the limit, select your role; this window can remain open if you'll use the assign button on the right side of your screen.

    If you'll let me know your results I can try to support you more.

     

    Regards

    Dieter 