Showing "% Complete" on Y-Axis of resource profile in P6.7
In the Open Standard
Sam .Member for 17 years 1 month
- Created
- 1
- 2
0
Hi All,
I have searched for this answer but cannot find,
At the moment my resource profile (S-curve) in P6 shows time on X-axis and units on Y-axis. (Standard format)
What box do I tick to instead show "% complete" on the Y-axis (based on budgeted units, not actual values)
I have tried changing "Time Units" to "Show as Percentage" in the User Preferences, no change.
Many thanks
Sam D
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?