Showing "% Complete" on Y-Axis of resource profile in P6.7

Sam .Member for 17 years 1 month
Created
1
2
0

Hi All,

 

I have searched for this answer but cannot find,

 

At the moment my resource profile (S-curve) in P6 shows time on X-axis and units on Y-axis. (Standard format)

 

What box do I tick to instead show "% complete" on the Y-axis (based on budgeted units, not actual values)

 

I have tried changing "Time Units" to "Show as Percentage" in the User Preferences, no change.

 

Many thanks

 

Sam D

1 reply

Oldest first
  1. 0
    Baris Hazar ·

    Hi,You can partially achieve

    Hi,

    You can partially achieve this by dividing the resource allocation interval totals by the whole contract amount or discipline total. It depends the scope of S-Curve. (Resource Assignments-->(Right Pane) Display-->Spreadsheet Options) By doing this you will have a value between 0 and 1 on the Y axis and I think this can somehow facilitate the interpretation of S-Curve. 

    Changing "Time Units" to "Show as Percentage" in the User Preferences enables you to view all the data columns titled as '.... Units/Time' in percentage wise such as the ones in Resource Dictionary or under Resources tab of Activity Details Table.

    Regards,

     

    baris

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?