Level Of Effort - Resource Assignments
In the Open Standard
Jonathan VardyMember for 15 years 2 months
- Created
- 1
- 2
0
Hi all,
I have a LOE activity (named project management) that spans the length of a 3 year project, it has around 12 project based resources assigned to it. Currently I manually enter in there annual leave by zeroing out the hours in the resource assignment view, however when the project is scheduled it alters the assignments and I have to go back in and re-enter the data. Is there something I’m doing wrong / a way around this?
Currently running P6 v7
Regards,
Jonathan
1 reply