P6 - Additional 1 day duration

Ronn Chester BaluyotMember for 18 years 7 months
Created
1
1
0

In the programme I'm working using P6, I'm using "day" as the unit of time. I set Admin Preferences>Time periods to 24 Hours/Day. I did the same for the calendar. But for an activity with a 1 day duration, which will start on 08-Aug-11 00:00, it will be finished on 09-Aug-11 00:00. Actually it is the same for every activity of any duration. So if I will not show the time, if you look at the start and finis date, it is like having an additional 1-day for the duration. Anybody knows how to fixed this? I read some previous thread but I haven't found any solution. Thanks.

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Ronn It is like a fence -

    Hi Ronn

    It is like a fence - the dates are the fence posts and the gaps is the duration - there is always 1 more fence post than gaps.

    Maybe you can set your duration to 1 second before midnight - you can in Asta Powerproject.

    Best regards

    Mike Testro

Log in or join to reply