Problem with Total Float in P6

Labeeqh AhmedMember for 17 years 2 months
Created
7
3
0

Hi,

I am currently working on a Infra Project were i wont be using the resources or levelling part,whereas i have to manage with the sheduling part i had already made the shedule now revising it again but have to maintain the total float as zero ,can any one help me on it.

Thanks in advance

7 replies

Oldest first
  1. 0
    Jash Sales ·

    Hi Labeeqh, If you really

    Hi Labeeqh,

    If you really want to maintain your schedule with zero total float, use a series-connection of activities with FS relationship only. Another way is that if you have different sequence/link of activities with morethan 0 TF, then assigned a lag to activities equal to its total float to make it critical.

    Cheers,

  2. 0
    Mike Testro ·

    Hi Labeeqh The only way you

    Hi Labeeqh

    The only way you can set up a genuine zero total float programme is to have only one cascade usiing only FS links.

    In most construction programmes this would be pointless.

    Why not just take out all the links and set each task to Must Start On.

    If you try to make the adjustments described by Jash (which would work) your programme will be worthless for time control management.

    Even worse it will be blatantly obvious that you have fiddled the programme.

    Float is a valid part of a properly prepared programme and should arise naturally from the logic - don't try to hide it.

    Best regards

    Mike Testro

  3. 0
    Labeeqh Ahmed ·

    Thank You friends for the

    Thank You friends for the valuable feedback will surely work on those lines and check my program

  4. 0
    Labeeqh Ahmed ·

    Hi,What i have done is i have

    Hi,

    What i have done is i have given must start dates and revised the project and i have applied the actuals and also updated the project as per the status , but could not able to make the total float as ZERO when i gave it for review to my Reporting head he is admant on me making the total float ZERO and wants it but i am not able to make

    Will there be any problem if i have a negative Total Float or Positive one &  what difference does it make in the program because we are only using the sheduling part.And how can i come out of this Float part.

    Please help me out

     

    Best Regards

  5. 0
    Jay Stadler ·

    Just remove all

    Just remove all constriants.

    You wil have 0 float and your forecast woul be your earlydate (Including project must finish) 

  6. 0
    Labeeqh Ahmed ·

    Hi,The each activity has

    Hi,

    The each activity has different float,i am talking about the project duration float which must be zero

  7. 0
    Gary Whitehead ·

    Project duration float will

    Project duration float will be zero if you remove all constraints

Log in or join to reply