Milestones with actual dates for baseline

Ronn Chester BaluyotMember for 18 years 7 months
Created
3
2
0

I'm comparing this months progress and last months progress. I used last month's programme as a baseline for this month's programme and reflect it in the Gantt Chart. So since I'm using last month's programme as a baseline (just for comparison) there are actual dates for tasks and milestones. No problem with task dependent activities, the problem is with the milestones with actual dates. Instead of showing it behind the data date line, it was shown ahead of the data date line just like a planned date. Anyone knows how to solve this. Thanks.

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ron If a milestone has

    Hi Ron

    If a milestone has been reached and achieved you need to set completion at 100%.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    If you don't have the right

    If you don't have the right settings chosen, Primavera will display planned dates instead of actual for baseline projects.

    Check the link below for Paul Harris' excellent explanation of this issue

     

    http://www.eh.com.au/Technical%20Papers/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf

     

    Cheers,

     

    G

  3. 0
    Ronn Chester Baluyot ·

    Gary,That was very helpful.

    Gary,

    That was very helpful. Thak you very much.