Ongoing Tasks in P6
- Created
- 0
- 1
What is the best way to set up an activity that I want to run throughout the length of a project?
For example, I have an activity in my plan called "Updates to Risk Register"
This starts on 17-August-2011 and finishes on 20-Sep-2012
I have ticked the Started box in the Status tab.
When I run a schedule with an updated data date, I want the progress % complete to calculate based on the end date of the task, and not for me to have to work out how much remaining duration there is?
Should I set the % Complete Type to Physical, Duration or Units?
Any other advice on setting up these kinds of tasks in P6?
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?