Dear Planners,

  is it possible to generate Resource loading report in P6 as we did previously in P3 and transfer it excel?

Regards,

2 replies

Oldest first
  1. 0
    Hannes de Bruyne ·

    yes - use report

     yes - use report wizzard.

     

    Subject Area „Activity Resource and Role Assignments“ select „Time Distributed Data"  select columns, fields etc. Finaly output in ASCII File delimited as in EXCEL

    • Regards
  2. 0
    Sinan Fahmi ·

    Thanks alot Hannes de

    Thanks alot Hannes de Bruyne.......