Removing date from Start & Finish fields

Steve CampbellMember for 15 years 5 months
Created
4
3
0

I'm organizing a schedule for a service group.  This is an event that is being planned down to the minute.  Everything takes place the same day.

 

Does anyone know of a way (would presumably involved a global change) to remove the date from the start/finish columns and just leave the time displayed?

 

Thanks,

Steve

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Steve In Powerproject you

    Hi Steve

    In Powerproject you just format the date field to show HH-MM-SS from the format drop down.

    Surely P6 has a similar mechanism?

    Best regards

    Mike Testro

  2. 0
    Steve Campbell ·

    No, there's no such setting

    No, there's no such setting in P6.  I'm hoping someone has created a clever global change to solve this problem.

  3. 0
    Steve Campbell ·

    OK, here's a kind of solution

    OK, here's a kind of solution that I found to this:

    1. Do a global change and move Start and Finish data to user text 1 and user text 2. 
    2. Go through user text 1 and user text 2 and, using "Replace" get rid of the date, leaving only the time.
    3. Rename them Start and Finish.

    They're static and won't change without re-running the global change, but it gets around the problem. 

    Anyone else have a solution that would not result in static Start and Finish columns?

  4. 0
    Mike Testro ·

    Hi Steve You have just

    Hi Steve

    You have just revealed another reason why P6 is rubbish compared to Powerproject.

    Can you set the work period to seconds?

    Best regards

    Mike Testro