resource smoothening

Sunil BabuMember for 15 years 11 months
Created
1
2
0

Hi friends,

Anybody please explain defference between resource smoothening and resource levelling

Regards.

Sunil

1 reply

Oldest first
  1. 0
    Ronald Winter ·

    Both operations involve

    Both operations involve delaying activity starts in order to better manage resources.  Resource leveling delays any activity that would cause a resource requirement in excess of a stated maximum for any given time period.  P6 can perform this function.

     

    Resource smoothing does not concern itself with resource availability so much as it does the change in resourcing.  It attempts to delay activity starts so as to reduce or eliminate sudden resource build-ups or build-downs.  It attempts to assign a level resource requirement over time.  P6 does not have a function for resource smoothing.  P3 did have smoothing settings but this was not real resource smoothing either.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?