Original Duration Problem while Importing xml File to P6
- Created
- 5
- 3
Hi there all,
I have a schedule prepared in MSP and I import it to P6 as an xml file. Durations of the tasks in the imported file appears in Original Duration column (as expected). However, when I change the duration of a task in the Original Duration column in P6, the bar in the Gannt Chart does not get longer or shorter. It gets longer or shorter when I change the duration in the Remaining Duration column.
The question I want to ask is, which column in P6 are the durations in MSP imported to? Is it Original Durations column or Remaining Durations column? or something else?
Thanks in advance.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?