Skip to content

Original Duration Problem while Importing xml File to P6

Utku ÇilMember for 15 years 4 months
Created
5
3
0

Hi there all,

I have a schedule prepared in MSP and I import it to P6 as an xml file. Durations of the tasks in the imported file appears in Original Duration column (as expected). However, when I change the duration of a task in the Original Duration column in P6, the bar in the Gannt Chart does not get longer or shorter. It gets longer or shorter when I change the duration in the Remaining Duration column.

The question I want to ask is, which column in P6 are the durations in MSP imported to? Is it Original Durations column or Remaining Durations column? or something else?

Thanks in advance.

5 replies

Oldest first
  1. 0
    Utku Çil ·

    I found the answer in one of

    I found the answer in one of the previous posts in forum. "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab" need to be checked. the problem is solved then.

    regards to all

  2. 0
    Ron Beechey ·

    Not sure why one would ever

    Not sure why one would ever have this check box turned off.   Does anyone know of a reason why this is an option, "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab

  3. 0
    Ron Beechey ·

    Not sure why one would ever

    Not sure why one would ever have this check box turned off.   Does anyone know of a reason why this is an option, "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab

  4. 0
    Utku Çil ·

    Ron,The thing is it was not

    Ron,

    The thing is it was not me who has that specific checkbox turned off. When I import the xml file from MSP, it comes out to be unchecked by default. Since I was not aware of the function of the checkbox, I could not understand what was going on. Anyway, I solved the problem.
     

    Sorry to take your invaluable time.

     

    Regards,

  5. 0
    Ron Beechey ·

    I was interested in what the

    I was interested in what the use of the option is.   Good to know that during the import it gets shutoff.

     

    You have a good day

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?