Skip to content

Milestones In The Wrong Place

Grace SantosMember for 15 years 1 month
Created
4
4
0

Hi again!

This time I have milestones that are showing under activities that start on the same date as the milestone. How do I get the milestones above these activities???

Thanks,

Grace

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Grace In powerproject you

    Hi Grace

    In powerproject you just drag and drop milestones to wherever you want them to be.

    This seems like another reason not to bother with P6.

    Best regards

    Mike Testro

  2. 0
    Kumar S ·

    Grace.. One way you can do is

    Grace..

    One way you can do is sort the activities  by actiivity type in groups and sort.

     

    Cheers

     

  3. 0
    Alaa Al haj ·

    hi Grace did you try what

    hi Grace

    did you try what Kumar suggest

    i think this is the easiest way  

  4. 0
    Grace Santos ·

    Thank you!!! That is awesome,

    Thank you!!! That is awesome, it worked great. Thanks again, Grace

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?