Skip to content

How "Performance % Complete" is calculated in P6

Raja ShuklaMember for 15 years
Created
6
5
0

How "Performance % Complete" is computed in P6? What is the basis / formula?

 

Thanks in advance.

 

Regards

6 replies

Oldest first
  1. 0
    Gary Whitehead ·

    It depends on what technique

    It depends on what technique you select from the admin preferences. Below description of each technique is copied direct from P6 help:

     

     

    Technique for computing performance percent complete

    Activity % Complete: Choose to calculate earned value according to current activity completion percentages.

    Use WBS Milestones: Choose to calculate earned value by defining milestones at the WBS level and assigning a level of significance or weight to each of them. As progress occurs and you mark each milestone complete, the WBS element’s performance percent complete is calculated based on the weight of the milestone.

    0/100 % Complete: Choose to calculate earned value as 100 percent only after the activity ends.

    50/50 % Complete: Choose to calculate earned value as 50 percent after the activity starts and until the activity ends. After the activity ends, the activity's earned value is 100 percent.

    Custom % Complete: Choose to calculate earned value as a percentage you specify. This percentage applies after the activity starts and until the activity ends. After the activity ends, the activity's earned value is 100 percent.

  2. 0
    Amit Parmar (PMP) ·

    Hi Raja,To know how

    Hi Raja,

    To know how Performance Percent Complete is Calculated , check out this link at PrimaveraBlog http://primaverablog.in/2011/02/performance-complete-calculations-in-the-wbs-bar/

    Regards

    Amit

    Check out my Blog on Primavera at http://www.primaverablog.in

  3. 0
    Thabo Letlhake ·

    Hi AllDoes anyone know what

    Hi All

    Does anyone know what causes Performance % complete to increase even when there is no progress on the activity, and which setting to alter.

    Thanks

  4. 0
    Zoltan Palffy ·

    The Performance % complete is

    The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far.

    Having something quantifiable and measurable is always the best way to measure progress that could be manhours or commodities such as LF of conduit ect.

    Performance Percent Complete for the activity is based on Units Percent Complete. Activities without a Resource curve assigned to one or more of the Resource Assignments will use the Activity percent complete

  5. 0
    Andrew Seutane ·

    Hi, does anyone know how a

    Hi, does anyone know how a Technique for computing performance percent complete settings in Primavera P6 is done?

    Regards

    Andrew

  6. 0
    Rodel Marasigan ·

    You can set the performance

    You can set the performance Percent Complete on WBS module or window under Earned Value tab. See below:

    Performance-percent-Complete

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?