Skip to content

Resource Dependent VS Task Dependent

Ashik GBMember for 15 years 10 months
Created
4
3
0

Hello Guys,

 

Can any body please tell the difference between Resource Deependent & Task Dependent for an activity and how & where it affects the Schedule (i.e., at Original duration & at resource levelling)?

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,a task dependent

    Hello,

    a task dependent activity will be scheduled accoring to its own calendar, a resource dependent activity according to the resource calendar

    let's say you have a 5 day task starting Monday; the task calendar say the week is standard, 5 day workweek

    you the assign a resource working 5 days, whose calendar says she's not working on Wednesdays

    a) the task dependent activity will be scheduled Mon - Fri, and the resource will work on Wed

    b) a resource dependent activity will start on Mon, be off on Wed, and finish the second Mon at night to let the resource accomplish her 5 day work

    Hope this helps,

    Alexandre

  2. 0
    Moutaz Aldeib ·

    Dear Alexandre,   In resource

    Dear Alexandre,

     

    In resource dependent, why Sat and Sun. are considered off days, this means the program will consider 3 days off (Wed. for the resource and two days for the task), is it logic?

     

    Regards,

     

    Moutaz

  3. 0
    Ashik GB ·

    Hello Alex,   Thanks for your

    Hello Alex,

     

    Thanks for your respond..

    Basically i know the concept of that,but i want to know will there any change in the original duration by keeping the activity as resource dependent & if we want to level the resources what affect it will show in project completion?

     

    Because in the above example you said like as per the task dependent the activity will work on mon-fri but resource will be off on wed.. so on which basis the activity will calculate the original duration? 

  4. 0
    Khuong Do ·

    Hi,I wrote an article to

    Hi,

    I wrote an article to explain What is the difference between Activity type: Task Dependent and Resource Dependent in Primavera P6.

    You can read it here : https://doduykhuong.com/2018/03/15/what-is-the-difference-between-activity-type-task-dependent-and-resource-dependent-in-primavera-p6/

    Regards

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?